Route 20 Intersection Improvement

25% Design Approved

The Traffic & Sidewalk Committee and the Town Engineer presented the preferred design plan to the Select Board on January 21, 2020, which was approved for submission to the state to petition for the TIP. The presentation can be found below:

25% Design Submission

Background

The Traffic & Sidewalk Committee and Select Board have held a series of public information meetings since 2014 for the purpose of soliciting public feedback on the intersection improvements at Route 20 / Boston Post Road / Wellesley Street. This is following the intersection study, which was conducted in 2013.

The 2018 Annual Town Meeting approved funds to advance the project to the 25% design phase. The Town Engineer and Traffic & Sidewalk Committee worked with abutters and VHB Engineering to develop the plans for submission.